Skip to content
+90 505 397 7779
BÜYÜKAYLaw Office
  • About
  • Practice Areas

    View all
    • Immigration Law in Türkiye
    • Foreign Investment and Relocation Law
    • Real Estate Law in Türkiye
    • Family and Inheritance Law
    • Energy Law
    • Health Law
    • Criminal Law
  • Articles
  • Publications
  • Team
  • Contact
  • Türkçetr
  • Englishen
  • العربيةar
  • Русскийru
Contact
Energy Law

Energy Law

Unlicensed Electricity Generation in Türkiye: Limits & Steps (2026)

  1. Home
  2. /
  3. Articles
  4. /
  5. Energy Law
  6. /
  7. Unlicensed Electricity Generation in Türkiye: Capacity Limits and Application Steps

Published: November 3, 2026·Reading time: 9 min read

Author: Kenan Serhat BÜYÜKAY

Summarize with AI

ChatGPTClaudeGrokGeminiPerplexity

Links open in a new tab. AI summaries may contain errors and are not a substitute for legal advice.

Cover on unlicensed electricity generation in Türkiye: capacity limits, distribution company filing and connection steps

Short answer: Unlicensed electricity generation means that the facilities listed in Article 14 of Law No. 6446 can generate power without a licence or a company. For renewable plants the general limit is one megawatt or the ceiling set by the President; self-consumption plants at the same metering point have no ceiling, while plants tied to contracted capacity are capped at that capacity or twice it. Applications go electronically to the distribution company, and project approval is due within one year of the call letter.

Key takeaways

  • Unlicensed generation is an exemption from licensing and incorporation, limited to the facilities listed in Article 14 of Law No. 6446.
  • Renewable plants are generally capped at 1 MW or the ceiling set by the President; self-consumption plants have no upper limit.
  • Industrial, municipal and agricultural irrigation facilities may build up to twice their contracted capacity.
  • Applications are filed electronically with the distribution company, and the network operator decides on them.
  • Without project approval within one year of service of the call letter, the right to a connection agreement is lost.
Contents
  1. What is unlicensed electricity generation?
  2. How does it differ from licensed generation?
  3. What is the installed capacity limit for unlicensed generation?
  4. Which facilities have no upper limit?
  5. Plants tied to contracted capacity
  6. Where must the generation and consumption facilities be located?
  7. How do you apply for unlicensed electricity generation?
  8. Can the installed capacity be changed during the application?
  9. Who assesses the application?
  10. How does the technical assessment work and how long does it take?
  11. Priority ranking for solar and wind applications
  12. Which deadlines run after the call letter?
  13. Share transfers and surplus electricity
  14. What can you do if the application is rejected?
  15. Common mistakes

Unlicensed electricity generation allows the facilities listed in Article 14 of the Electricity Market Law (Elektrik Piyasası Kanunu, Law No. 6446) to generate power without a licence from EPDK (Energy Market Regulatory Authority) and without setting up a company. For renewable plants the Law sets a general installed capacity limit of one megawatt, while plants built at the same point as the consumption they serve, or capped by the contracted capacity in their connection agreement, follow different rules.

The application is filed electronically with the relevant distribution company, acting as network operator, and moves through document review, technical assessment, a call letter for the grid connection agreement and, finally, the agreement itself. Below we explain the capacity limits, the application steps and the points where applicants most often lose their rights in practice, based on the Regulation on Unlicensed Electricity Generation in the Electricity Market (Elektrik Piyasasında Lisanssız Elektrik Üretim Yönetmeliği, the Regulation).

What is unlicensed electricity generation?

Unlicensed electricity generation is power production that is exempt from both the licensing requirement and the obligation to set up a company. The exemption covers only the facility types listed in Article 14(1) of Law No. 6446. If your project is not one of them, you will need to go through the pre-licence and licence process.

The main facilities listed in the Law are emergency generator sets and off-grid installations, renewable plants with an installed capacity of up to one megawatt, municipal solid waste and sewage sludge facilities, micro-cogeneration plants and cogeneration plants of a set efficiency, and renewable plants whose entire output is consumed at the same metering point. Amendments made in 2020 and 2022 added renewable plants tied to contracted capacity to this list.

How does it differ from licensed generation?

In licensed generation, the investor applies to EPDK first for a pre-licence and then for a generation licence, and as a rule carries on the activity through a company. Unlicensed generation removes the pre-licence, licence and incorporation requirements, and the process runs through the distribution company instead. In return, an unlicensed plant is confined to the capacity, location and consumption-link conditions defined in the Law and the Regulation.

This difference also shapes the financing and ownership structure of a project. An unlicensed plant is, in principle, linked to a consumption facility; projects designed only to sell power on the market should generally be assessed under the licensed regime. Before making the investment decision, it should be clear which regime the plant falls under.

What is the installed capacity limit for unlicensed generation?

The general rule is that the installed capacity of a renewable plant may not exceed one megawatt. The Law authorises the President to raise this ceiling up to five times on a source-by-source basis. The Regulation likewise refers to 'one megawatt or the installed capacity ceiling set by the President'; confirm the ceiling currently in force against EPDK's latest announcements.

Which facilities have no upper limit?

Under the Regulation, the installed capacity ceiling does not apply to certain facility types. Chief among them are self-consumption plants whose generation and consumption share the same metering point, off-grid installations and efficient cogeneration plants. Having no ceiling does not mean unlimited capacity, however: the plant is still bound by its consumption need and by the technical capacity of the grid.

Plants tied to contracted capacity

Municipalities and their affiliates, industrial facilities and agricultural irrigation facilities may build renewable plants of up to twice the contracted capacity stated in their connection agreement. For everyone else, the limit is the contracted capacity itself. A plant in this category may sit at the same metering point as the consumption facility or at a different one.

Table of capacity limits for general renewable, self-consumption, contracted-capacity and off-grid unlicensed power plants
Installed capacity limits by facility type

Facility type

Capacity limit

Legal basis

Renewable energy plant (general)

1 MW or the ceiling set by the President

6446 s.K. m. 14/1-b; Yönetmelik m. 5/1-c

Self-consumption at the same metering point

No upper limit

Yönetmelik m. 5/1-ç ve 5/6

Municipal, industrial, agricultural irrigation

Twice the contracted capacity

6446 s.K. m. 14/1-g; Yönetmelik m. 5/1-h

Other consumers (tied to contracted capacity)

Up to the contracted capacity

6446 s.K. m. 14/1-g

Off-grid installation

No upper limit

Yönetmelik m. 5/1-b ve 5/6

Where must the generation and consumption facilities be located?

As a rule, the generation facility and the consumption facility must be located in the same distribution region. For plants tied to contracted capacity, however, the Regulation allows the generation facility to be built outside the distribution region where the consumption facility is located. Check this distinction before you choose the land.

Where the grid has enough capacity, more than one renewable plant with the same support structure may be permitted for a single consumption facility. A person may, however, build only one micro-cogeneration plant for each consumption facility they hold. This rule was rewritten by an amendment published in the Official Gazette (Resmî Gazete) on 2 April 2026.

How do you apply for unlicensed electricity generation?

The application is submitted electronically to the relevant network operator, together with the information and documents specified by decision of the EPDK Board. Apart from obligations arising under other legislation, the network operator may not reject an application because a document that is not on that list is missing. Documents received electronically are not returned.

  • Identify the facility type: self-consumption, tied to contracted capacity or a general renewable plant?
  • Prepare the subscription and contracted capacity details of the consumption facility and its consumption data for the last year.
  • Check the document list set by Board decision on the websites of EPDK and the distribution company.
  • File the application electronically with the network operator, and do not file duplicate applications for the same site in the same name.
  • Monitor the website where document review and technical assessment results are announced.
  • If the result is positive, request the call letter in time and start the project approval process.

Can the installed capacity be changed during the application?

The applicant may request a change of installed capacity in writing within the month in which the application was filed. In that case the date of the change request counts as the application date, and the documents required for the new capacity are added to the file. Changes requested after that month are governed by different rules.

If the applicant asks in writing for data needed for the application that by its nature can be obtained from the network operator, the operator must provide it in writing within three business days. The 2026 amendment also bars the same person from filing a second application for the same site before the first one is decided; if the earlier application is withdrawn, the new one is not treated as a duplicate.

Who assesses the application?

Applications are examined on documents and technical merits by a commission set up within the network operator. At distribution companies, the commission consists of one representative each from TEİAŞ (Turkish Electricity Transmission Corporation), TEDAŞ (Turkish Electricity Distribution Corporation) and the network operator concerned; it decides by majority vote and is chaired by the TEİAŞ representative.

The power to receive, assess and conclude applications belongs to the network operator. For this reason, in the case law of the Council of State (Danıştay), applying directly to EPDK for an application to be accepted has not been seen as a route that produces a result.

Court decisionCouncil of State (Danıştay), 13. Daire

E. 2016/4752, K. 2022/3424 · 09/29/2022

The power to receive, assess and conclude unlicensed generation applications lies with the network operator; since EPDK cannot lawfully conclude a request filed directly with it for acceptance of an application, the implied rejection is lawful (the administrative court's judgment was upheld).

6446 s.K. m. 14; Lisanssız Elektrik Üretim Yönetmeliği

How does the technical assessment work and how long does it take?

Applications found to be complete are technically assessed within twenty days of the month following the month in which the document review took place. Applications for which TEİAŞ reports that the fault current limit or the transformer capacity at the substation is exceeded are rejected without a technical assessment. Applications are grouped by transformer substation and examined on the basis of the connection point.

Priority ranking for solar and wind applications

Where capacity at the same connection point is insufficient, the Regulation's priority criteria are applied to wind and solar applications in the following order. If more than one application meets all the criteria, the application date determines the ranking.

  • the generation facility is at the same metering point as the consumption facility it will be linked to;
  • the applicant's consumption over the last year (or the consumption used for the priority assessment) is higher;
  • the contracted capacity in the connection agreement is higher;
  • the applicant has no earlier application that received a positive connection opinion.

Assessment results are published on the network operator's website within the business day following the assessment date. The applicant is notified in writing within three business days, and a rejection notice must set out the reasons for the rejection and the technical assessment.

Flow of an unlicensed generation application: filing, document review, technical review, notice, call letter, agreement
From application to the grid connection agreement

Which deadlines run after the call letter?

A person served with the call letter for the grid connection agreement is given one year from the date of service. Within that year, the generation facility project and, if there is one, the connection line project must be approved by the Ministry or an institution the Ministry has authorised.

If the project approval and, for hydro plants, the water use rights agreement are submitted in time and in full, the network operator must sign the grid connection agreement within thirty days. If the documents cannot be submitted within the one-year period, the right to sign the grid connection agreement is lost.

Share transfers and surplus electricity

For wind and solar plants that fall under the Law's general one-megawatt limit, shares may not be transferred from the application date until provisional acceptance of all the facilities, except in cases exempted by the EPDK Board. If shares are transferred, the call letter for the grid connection agreement is cancelled.

Electricity generated beyond the facility's needs and fed into the grid is handled through the incumbent supply company under YEKDEM (Renewable Energy Support Mechanism). Transactions relating to sales and netting can be challenged with the incumbent supply company or the aggregator within three business days of notification.

What can you do if the application is rejected?

First, establish whether the rejection is based on missing documents, grid capacity or the priority ranking. Under the Regulation, the reasons must appear in the written notice, and the right course of action depends on them.

In administrative proceedings, the time limit for filing an action is sixty days from written notification, unless a specific law sets a different period (İYUK m. 7, İdari Yargılama Usulü Kanunu, the Administrative Procedure Law). Whether the distribution company's decision counts as an administrative act, and which court has jurisdiction, must however be assessed for the specific act. That is why it is important to keep a record of the date on which the rejection notice was served.

For rejections based on insufficient capacity, the capacity to be announced for the same transformer substation in the coming months and the option of a different connection point can be considered. For rejections based on missing documents, check whether the document really appears on the list set by Board decision; an application cannot be rejected over a document that is not on that list.

Common mistakes

  • Misidentifying the facility type and filing under a provision that does not fit the project.
  • Leasing land without checking that the generation and consumption facilities are in the same distribution region.
  • Not following the result announcements and missing the period for requesting the call letter.
  • Failing to complete project approval within one year and losing the right to a connection agreement.
  • Transferring company shares before provisional acceptance and triggering cancellation of the call letter.
  • Not recording the date the rejection was served and leaving the time limit for legal action uncertain.

For foreign companies and investors involved in such a project: under Article 32(2) of the Trade Registry Regulation (Ticaret Sicili Yönetmeliği), documents issued abroad under foreign law must be certified by a Turkish consulate or under the Hague Apostille Convention and filed with the trade registry together with a notarised Turkish translation. According to the HCCH status table, the Convention has been in force for the United Kingdom since 24 January 1965, for the United States since 15 October 1981 and for Türkiye since 29 September 1985. In the UK, the FCDO Legalisation Office issues apostilles, and documents such as powers of attorney must first be certified by a UK notary or solicitor; in the US, state-issued documents are apostilled by the authorities of the issuing state and federal documents by the Department of State's Office of Authentications. Confirm the exact document list with the trade registry directorate and the network operator before filing.

With the right facility type and timely steps, unlicensed electricity generation is a predictable process; however, the Regulation was amended again in 2025 and 2026, so every application calls for a check of the current text. For a legal roadmap before your project, review our scope of services in energy law; you can browse our other articles on the Our Work page and send us your questions via the Contact page.

Frequently asked questions

  • Do I need to set up a company for unlicensed electricity generation?+

    No. The facilities listed in Article 14 of the Electricity Market Law are exempt from both licensing and the obligation to set up a company, so individuals can apply as well. The exemption, however, covers only the facility types listed in the Law and the Regulation; any generation activity outside that scope must go through the pre-licence and licence process with EPDK.

  • What is the installed capacity limit for unlicensed generation?+

    Under the Law, the general limit for renewable plants is one megawatt, and the President may raise it up to five times on a source-by-source basis. Self-consumption plants at the same metering point have no upper limit, while plants tied to contracted capacity are capped at that capacity or twice it. Confirm the ceiling currently in force with EPDK.

  • Where is the application filed?+

    The application is filed electronically with the relevant network operator, which in most cases is the regional electricity distribution company, together with the information and documents set by EPDK Board decision. For applications at transmission level, all three members of the commission are TEİAŞ representatives. The power to assess and conclude the application lies with the network operator, not with EPDK.

  • How long does the technical assessment take?+

    Complete applications are technically assessed within twenty days of the month following the month of document review. Results are announced on the network operator's website within the next business day, and the applicant is notified in writing within three business days. The overall timeline depends on the month in which you apply and on the available grid capacity.

  • How much time is given after the call letter?+

    You have one year from service of the call letter for the grid connection agreement. Within that year, the generation facility project and any connection line project must be approved. If the required documents are submitted in full, the network operator signs the connection agreement within thirty days; if they are not submitted in time, the right to sign it is lost.

  • Can the generation plant be built in another province?+

    As a rule, the generation and consumption facilities must be in the same distribution region. For renewable plants tied to contracted capacity, built by municipalities, industrial facilities, agricultural irrigation facilities and other consumers, the Regulation does allow the generation plant to be located outside the distribution region where the consumption facility is.

  • How is priority decided between solar applications?+

    If capacity is insufficient, the criteria are applied in this order: generation and consumption at the same metering point, higher consumption over the last year, higher contracted capacity, and no earlier application with a positive connection opinion. Where several applications meet all of these criteria, the application date decides the ranking.

  • What happens to surplus electricity?+

    Electricity generated beyond your needs and fed into the grid is handled through the incumbent supply company under the Renewable Energy Support Mechanism (YEKDEM). Sales and netting transactions can be challenged with the incumbent supply company or the aggregator within three business days of notification. The pricing rules and the quantity eligible for sale should be checked separately.

  • Can shares be transferred in an unlicensed solar project?+

    For wind and solar plants within the Law's general one-megawatt limit, shares may not be transferred from the application date until provisional acceptance of all facilities, except for exceptions set by the EPDK Board in regulation. A transfer leads to cancellation of the call letter for the grid connection agreement, so investment partnerships should be structured with this ban in mind.

  • My application was rejected. Can I take legal action?+

    A rejection notice must state its reasons and include the technical assessment, so the first step is to review those reasons. In administrative proceedings, the general time limit for filing an action is sixty days from written notification. The nature of the distribution company's decision and the competent court must be assessed case by case, so keep a record of the date of service.

Author

Kenan Serhat BÜYÜKAY

Attorney at Law

Attorney Kenan Serhat BÜYÜKAY brings professional experience from Türkiye and the United States to citizenship and immigration law, as well as to commercial law and several areas of international law, advising and representing Turkish and international clients.

Related practice areas

  • Energy Law

This article is for general information only; consult an attorney for advice on a specific matter.

BÜYÜKAYLaw Office

Select language

  • Türkçe
  • English
  • العربية
  • Русский

Firm

  • About
  • Team
  • Articles
  • Publications
  • Contact
  • Search

Practice Areas

  • Immigration Law in Türkiye
  • Foreign Investment and Relocation Law
  • Real Estate Law in Türkiye
  • Family and Inheritance Law
  • Energy Law
  • Health Law
  • Criminal Law
  • View all

Contact

Hukukçular Towers, Mustafa Kemal Paşa Caddesi, Seyitgazi Sokağı, No: 66 A Blok D: 15Kartal / İSTANBUL

+90 505 397 7779WhatsApp

Monday–Friday 09:00–18:00

This website has been prepared in accordance with the Advertising Ban Regulation of the Union of Turkish Bar Associations. Information on this site is of a general nature and does not replace legal advice.

© 2026 BÜYÜKAY